Standard Sprint Planning with Overcommitment Detection

Analyzes a stable team's historical velocity to identify severe overcommitment (108% over capacity) and provides specific story recommendations for commit, stretch, and defer categories.

Input

What you provide to the skill

6 developers, 2-week sprint. Last 5 sprints: 25, 28, 27, 26, 29 points. Candidate stories: auth (8), dashboard (13), CSV (5), notifications (8), rate limit (5), optimization (8), bugs (3).

Output

What the skill generates for you

SPRINT COMMITMENT ANALYSIS

Historical Performance:

  • Last 5 sprints: 25, 28, 27, 26, 29 points
  • Average velocity: 27.0 points
  • Velocity trend: STABLE (±2 points variation)
  • Standard deviation: 1.4 points (5% of average)
  • Predictability: HIGH (low variance)

Recommended Commitment Ranges:

  • Conservative (80% of avg): 22 points
  • Standard (90% of avg): 24 points ← RECOMMENDED
  • Aggressive (100% of avg): 27 points

Why Standard (90%)? Your team has stable, predictable velocity with low
variance. A 10% buffer protects against minor surprises while maintaining
good throughput.

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

CURRENT SELECTION ANALYSIS:

  • Proposed stories: 50 points
  • Capacity utilization: 208%
  • Risk level: CRITICAL
  • Expected completion: 54% of planned stories (27/50 points)
  • Likely spillover: 23 points

WARNING: Your team is overcommitting by 108%.

Based on 5 sprints of historical data, your team consistently completes
~27 points. Committing to 50 points will result in:

  • ~23 points of incomplete work
  • Potential team morale impact from “failed” sprint
  • Stakeholder frustration with unpredictable delivery
  • Rushed work or cut corners in final days

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

RECOMMENDED STORY SELECTION (24 points - Standard commitment):

COMMIT TO THESE:

  1. auth (8 points)
  2. notifications (8 points)
  3. CSV (5 points)
  4. bugs (3 points)

Total: 24 points (89% of average velocity)

STRETCH GOALS (add if ahead of schedule):

  • rate limit (5 points)

DEFER TO NEXT SPRINT:

  • dashboard (13 points) ← Consider breaking into smaller stories
  • optimization (8 points)

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

INSIGHTS & RECOMMENDATIONS:

Velocity Stability: Excellent predictability (std dev only 5%). Planning
is reliable.

Realistic Commitment: 24-point selection leaves 10% buffer (2-3 points) for:

  • Unexpected production bugs
  • Scope clarification discussions
  • PR review cycles
  • Minor technical unknowns

Large Story Warning: dashboard (13 points) is nearly 50% of sprint
capacity. Consider breaking down:

  • Dashboard layout/navigation (5 points)
  • Dashboard widgets/data (5 points)
  • Dashboard performance/polish (3 points)

Risk Assessment: With recommended selection, risk of incomplete sprint: LOW (15%)
Success Probability: 85% chance of completing all committed stories + stretch goals